We have been blessed with good weather for past few weeks which has allowed our building crew to get a lot of work done. |
K8 had to finish some drain lines along both retaining walls. |
The basement walls are finished. |
The floor joists are completed. K6 is on the left entering the basement. |
The pre-built exterior walls, and then the pre-built interior walls, all went up in a day and a half! |
And then we were ready for the crane to lift the rafters up into place - done in four hours. |
The back porch concrete was poured just a few days earlier. Once the rain stops this week, we'll be putting up the 6" X 6" posts along the back and start build the back deck. |
Looking good. |
We have been blessed with a good crew and lots of good sub-contractors. |
Unfortunately, there were a few victims of our house building. We had to remove four trees, oak and hickory. It took us a week to get them cut, split. |
The rural electric co-op sent a crew to take down 2 of the 3 Sycamore trees in paddock #6. |
Wow! The house is moving right along, looking good Whipple Wanch Workers :)
ReplyDeleteCan't wait to see it finished and getting Gramma in there!!!
ReplyDelete